“Sennit Construction demonstrated excellent project management and coordination throughout the works at Govan Primary School.

They maintained strong communication, adhered to the programme, and delivered a high-spec roofing system to a very high standard.

Their collaborative approach with Bauder and sensitivity to the live school environment made them a reliable and professional contractor to work with.” – Project Manager, Govan Primary School

  • Client: Galliford Try FM (Facilities Management)
  • Location: Govan Primary School, Glasgow
  • Project value: £700,000
  • Building type: Children’s school/live environment
  • Services delivered: Flat roof strip & renew (felt roofing), thermal upgrade, rooflight management, perimeter detailing, refurbishment outlets
  • Supply chain partners: Bauder (specification + technical support)

Remove the deteriorating flat roof system and install a new, modern, high-performance built-up felt roofing solution that delivers long-term waterproofing, improved durability and enhanced thermal efficiency.

All while safeguarding controls appropriate for a live school setting.

The challenge

Even when works are programmed during holidays, school sites demand a higher standard of control and responsibility. The key pressures included:

  • A deteriorating roof that needed safe access and edge protection across a large flat roof area
  • Secure site boundaries and controlled access to protect staff, visitors and the wider school environment
  • Noise sensitivity and management to minimise disruption to learning, with additional precautions near the autism support units and playground
  • Hot works management for a torch-applied cap sheet
  • A fixed 10-week programme with contingency planning in case of any overlap with term time
  • Temporary removal and protection of roof skylights during strip-out and installation
  • Maintaining emergency escape routes and keeping the site tidy and safe, every day

Our solution:

We planned works to reduce disruption: sequencing noisy activities, controlling access routes, and coordinating with school leadership so everyone knew what to expect and when. We also had a dedicated welfare compound and on-site first aider, with supervisor-led briefings and inductions.

Segregated work zones, secure scaffold access planning, and clear site rules were embedded from day one:

  • Robust fire-safe working practices for the torch-applied cap sheet
  • Roof access via scissor lift with triple handrail edge protection
  • Emergency scaffold tower installed within the internal courtyard
  • Full Heras-fenced compound with locked access

We carried out a full strip of the existing flat roof system, with responsible waste disposal and regular waste removal to prevent build-up and maintain a safe working surface throughout.

The roof was upgraded to meet current building regulations, improving energy efficiency and comfort inside the school. We installed a complete Bauder built-up felt system with careful detailing to ensure long-term waterproof integrity.

Why the Govan Primary School roof refurb matters

A school roof isn’t just a building, it protects learning, safety, and day-to-day routines. This refurbishment was about delivering long-term performance without compromising safeguarding or site control. The result is a warmer, more resilient school building, and a project delivered with the kind of care you want around children and staff.